The sum per day for each day of delay due to the reason that the contractor not completing the work in the scheduled time (or also within the extended time, if

allowed by the authorities on valid grounds) due charge is levied on him is known as 

1
Liquidated damage
2
Ascertained damage 
3
Both 1 & 2
4
Contingencies
5
None of the above