Which one of the following statements is not correct?

1
PERT is event oriented & CPM is activity oriented
2
CPM is event oriented & PERT is activity oriented
3
Both PERT & & CPM are used for project estimations techniques
4
In PERT, three-time estimates are made for each activity and is CPM only one-time estimate are made for each activity.