engineering recuitment Vizag Steel MT Mechanical 2020 Test Series Industrial Engineering Operations Research PERT and CPM
The estimated duration of times for an activity in a PERT network under the worst and best environment is 18 and 12 days. The variance of this activity is ______ day.
1
0.5
2
1
3
2
4
0.25