engineering recuitment Vizag Steel MT Mechanical 2020 Test Series Industrial Engineering Production Planning and Inventory Control Forecasting
Using exponential forecast method, forecast of 11th week when demand and forecast of 10th week are 480 and 500 with α = 0.2
1
504
2
490
3
496
4
484