Samiksha does 40% of work in 10 days. She then calls Manjiri and they together finish the remaining work in 6 days. How many days Manjiri would alone take to do the whole work?

1
\(15\frac{1}{3}\)
2
\(15\frac{2}{3}\)
3
\(16\frac{2}{3}\)
4
\(17\frac{2}{3}\)