Industrial Engineering Production Planning and Inventory Control Material Requirement Planning (MRP)
In Materials Requirement Planning, if the inventory holding cost is very high and the setup cost is zero, which one of the following lot-sizing approaches should be used?
1
Economic Order Quantity
2
Lot-for-Lot
3
Base Stock Level
4
Fixed Period Quantity, for 2 periods