A and B together can do a work in 16 days, which B and C together can do in 32 days. After A has been working at it for 15 days and B for 13 days, C finished it in 10 days. In how many days A and C alone will do the work respectively?
1
\(12\frac{2}{7}\) days and 108 days
2
24 days and 96 days
3
31 days and 124 days
4
48 days and 54 days