engineering recuitment HAL Management & Design Trainee Mock Test 2023 Industrial Engineering Operations Research PERT and CPM
Which of the following artificial activity suggests that an activity following it cannot happen unless, the previous activity is completed?
1
Event
2
Dummy
3
Constant
4
Free float