engineering recuitment HAL Management & Design Trainee Mock Test 2023 Industrial Engineering Production Planning and Inventory Control Line Balancing and Work Study
An industry produces 300 spark plugs in one shift of 8 hours. If the standard time per piece is 1.5 minute, the productivity would be
1
3/4
2
5/8
3
7/16
4
15/16