Fifty observations of production operation revealed a mean cycle time of 10 min. The worker was evaluated to be performing at 90% efficiency. Assuming the allowances to be 10% of the normal time, the standard time (in minutes) for the job is
1
0.198
2
7.3
3
9.0
4
9.9