engineering recuitment ISRO Scientist Mechanical Mock Test Industrial Engineering Production Planning and Inventory Control Forecasting
The demand and forecast for February are 12000 and 10275, respectively. Using single exponential smoothening method (smoothening coefficient = 0.25), forecast for the month of March is
1
431
2
9587
3
10706
4
11000