engineering recuitment RVUNL JEn (RSEB) Mock Tests 2025 Power Systems Economies of Power Generation Load Factor
The maximum demand of a power station is 100 MW. If the annual load factor is 40%. Calculate the total energy generated in a year:
1
3.5 × 105 kWh
2
3504 × 105 kWh
3
3504 × 106 kWh
4
35.04 × 105 kWh
5
None of these