engineering recuitment Rajasthan Housing Board JE Civil (Degree & Diploma) Mock Test 2023 Construction Materials and Management Project Planning PERT
The optimistic, most likely and pessimistic time estimates for an activity are 6, 16 and 22 days, what could be the probabilistic time estimate
1
15.33 days
2
30.66 days
3
14.66 days
4
29.33 days