If saturation headway of given traffic is 2.5 sec and the cycle time on a particular intersection is 65 sec, with green time as 25 sec and corresponding yellow time as 3.5 sec. If the start-up loss time is 2 sec and clearance time is 1 sec, then find the actual capacity of the vehicle per lane in veh/hour.
1
380
2
604
3
565
4
459