For a particular job, four different firms have submitted the time estimates and they are

Firm

Optimistic time (t0)

Most Likely Time (ti)

Pessimistic Time (tP)

A

5

10

13

B

6

9

12

C

5

10

14

D

4

10

13

 

Which one of these firms is more certain about completing the job in time?

1
B
2
D
3
A
4
C