Which of the following is/are the main drawback (s) in adopting bar charts?
1. All the activities are shown as being independent of each other
2. The sequence of activities not defined at all
3. It is difficult to judge whether an activity is completed or not
1
1 only
2
2 only
3
3 only
4
1, 2 and 3