engineering recuitment KPSC Assistant Engineer Civil Mock Test 2020 Construction Materials and Management Construction Management
The purpose of work-break-down structure in project planning is mainly to
1) Facilitate and improve the decision-making on procurement of resources .
2) Relate activities under particular trade specializations to help in organizing for project staff
3) Co-ordinate regarding milestone events across trade specialization to improve the synergy between the trades1
1 and only
2
1 and 3 only
3
2 and 3 only
4
1, 2 and 3