Consider the following statements:
1. The resources are considered to be limited.
2. The duration of the project is not changed.
3. The start times of some of the activities are so shifted within their available floats that the uniform demand is created for the resources.
Which of the following statements/s are correct regarding resource levelling?1
1 and 3 only
2
2 and 3 only
3
2 only
4
1, 2 and 3 only