When the sanctioned estimate is likely to be exceeded by more than 5% either from the insufficient fund or, price level, or whatever, other than structural alteration, then
the estimate which is prepared is called:
1
supplementary estimate
2
unit rate estimate
3
detailed estimate
4
revised estimate