The importance of subgrade drainage and compaction was recognized and so the subgrade was compacted and was prepared with a cross slope of 1 in 36. In which type of Road Construction, the above statement came into picture?
1
Tresaguet Construction
2
Telfords Construction
3
Macadam Construction
4
Metcalf Construction