Which of the following statements is INCORRECT with respect to the calculation of LST (Latest Start Time) for the activities involved in a network diagram?

1
At the end event LST is equal to Zero
2
The calculation of LST starts from end event
3
The computations are done through backward pass method
4
The computations of LST usually proceeds right to left