In the estimation of quantities of the following works (given with codes M, N, O, P), identify the work having a different unit of measurement with respect to others?
M. Turfing of bunds of a canal
N. Wood work for door shutters
O. Bituminous road surfacing
P. Grouting of cracks or joints
1
N
2
O
3
M
4
P