Which one of the following is an INCORRECT statement?

1
Fulkerson's rules can be used for numbering the events.
2
A project network diagram can have only one critical path.
3
Knowledge of the precedence relationship between activities is necessary for making the project network diagram.
4
Network diagram is an essential part of the CPM and PERT technique.