Calculate the critical path for the following project's activities:
Activity Predecessors Duration (days)
A - 3
B A 4
C A 5
D A 4
E B 2
F D 9
G C, E 6
H F, G 2

1
A-B-E-G-H
2
A-D-F-H
3
A-C-G-H
4
A-B-C-F-H