engineering recuitment OSSC Combined Technical Services (ଓଡିଶା) Mock Test 2023-24 Estimating, Cost and Valuation Measurement
One mason in one day is expected to do the brick work in lime or cement in foundation and plinth with beldars are
1
1.00 m3
2
1.25 m3
3
1.50 m3
4
1.75 m3