engineering recuitment OSSC Combined Technical Services (ଓଡିଶା) Mock Test 2023-24 Construction Materials and Management Project Planning
Which of the following is a disadvantage of Just in Time (JIT) inventory management in construction projects?
1
Increased lead times
2
Excessive material handling
3
Greater risk of material shortages
4
Higher storage costs