engineering recuitment FCI JE 2022 Mock Test for CE/ME/EE (Phase I & II) Construction Materials and Management Project Planning PERT
The project given below follows PERT analysis whose expected duration of completion is 8 days. The pessimistic time for activity AB of the project is
1
5 days
2
6 days
3
7 days
4
8 days
5
10 days