engineering recuitment FCI JE 2022 Mock Test for CE/ME/EE (Phase I & II) Construction Materials and Management Project Planning PERT
Lag time is the
1
time by which an event preceded by it must be completed.
2
earliest time by which a successor event can follow a specific PERT event.
3
time performing more critical activities in parallel.
4
measure of the excess time resources available.
5
earliest time by which a successor event can follow a specific CPM event.