engineering recuitment FCI JE 2022 Mock Test for CE/ME/EE (Phase I & II) Construction Materials and Management Project Planning PERT
In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)
1
0%
2
100%
3
Less than 100%
4
50%
5
60%