A power station has 4 consumers with their maximum demand as 40 MW, 20 MW, 30 MW and 50 MW. The maximum demand of the station is 100 MW. The diversity factor of the plant is ______.
1
0.5
2
0.2
3
1.4
4
0.35
5
1.6