engineering recuitment FCI JE 2022 Mock Test for CE/ME/EE (Phase I & II) Construction Materials and Management Project Planning PERT
Find the total duration of the network of a construction project work shown in figure.
1
21 days
2
17 days
3
25 days
4
29 days
5
42 days