engineering recuitment FCI JE 2022 Mock Test for CE/ME/EE (Phase I & II) Estimating, Cost and Valuation Valuation
The length, breadth, and depth of an excavated earthwork are 6 m x 0.8 m and 0.9 m. calculate the total amount required for excavation if the rate of excavation per cubic meter is Rs. 300.
1
Rs. 1472
2
Rs. 1296
3
Rs. 1100
4
Rs. 1491
5
Rs. 1000