engineering recuitment FCI JE 2022 Mock Test for CE/ME/EE (Phase I & II) Soil Mechanics and Foundation Engineering Consolidation
A clay layer 10 m thick in the field takes 400 days to attain 50% consolidation with the condition of double drainage. If the same clay layer is underlain by a hard rock then the time taken to attain 50% consolidation is:
1
100 days
2
800 days
3
1000 days
4
200 days
5
1600 days