engineering recuitment NCL Assistant Foreman (Trainee) Mock Test 2024 Quantitative Aptitude Time and Work Work Efficiency
Twelve men can complete a work in 8 days. Three days after the work 3 more men joined. In how many days will all of them together complete the remaining work?
1
2
2
4
3
5
4
6