The time is taken by A, B and C together to complete a piece of work is \(\frac{300}{37}\) days. If the working efficiency of A and B is 5 : 4, and the working efficiency of B and C is 6 :5, then find the time taken by A and C together to complete 33.33% of the work.
1
37 days
2
4 days
3
13 days
4
10 days