A generating station has a maximum demand of 25 MW, a load factor of 60%, a plant capacity factor of 50% and a plant use factor of 72%.
The maximum energy that could be produced daily if the plant while running as per schedule, were full loaded is ______1
400 MWh/day
2
300 MWh/day
3
200 MWh/day
4
500 MWh/day