engineering recuitment Bihar LRC AMIN JE Civil Mock Test 2023 Industrial Engineering Operations Research PERT and CPM
In CPM network critical path denotes the:
1
path where maximum resources are used
2
path where minimum resources are used
3
path having zero delay
4
path that gets monitored automatically.