engineering recuitment Bihar LRC AMIN JE Civil Mock Test 2023 Construction Materials and Management Concrete
Today the casting of the 8-meter wide beam has been done. What will be the minimum time (days) for the support of the beam to be removed?
1
14
2
7
3
21
4
28