Match List – I and List – II, and select the correct answer using the codes in given below list.

List-I

List-II

i.

Preliminary estimate

1.

Probable variation for quantity rate and amount for each items

ii.

Revised estimate

2.

Material deviation of a structural nature

iii.

Supplementary estimate

3.

Complete estimate

iv.

Quantity estimate

4.

Approximate cost of the project

1
i – 4, ii – 1, iii – 2, iv - 3
2
i – 4, ii – 2, iii – 1, iv - 3
3
i – 3, ii – 1, iii – 2, iv - 4
4
i – 3, ii – 2, iii – 1, iv - 4