engineering recuitment UKPSC AE Civil 2021 Mock Test (Re-Exam) Construction Materials and Management Project Planning PERT
The time by which the starting or finishing of an activity can be delayed without affecting the succeeding, as well as preceding activities is called _______ float.
1
total
2
free
3
independent
4
interfering