A motor has to supply the following load cycle to a varying load: 20 kW for 10 seconds, 10 kW for 20 seconds, 30 kW for 10 seconds and idle for 10 seconds in one load cycle. What will be the size of the motor required?
1
\(\sqrt {300}\) kW
2
\(\sqrt {350}\) kW
3
\(\sqrt {375}\) kW
4
\(\sqrt {325}\) kW