Which one of the following statements is correct?
1
PERT is commonly used in the construction work.
2
PERT is suitable for the estimation of activity duration where high levels of uncertainty is there.
3
PERT does not provide time duration.
4
PERT is a deterministic approach. for estimating the time duration of an activity.