engineering recuitment GATE CE 2023-24 Test Series Construction Materials and Management Construction Management
A small construction project consists of the jobs as given in the table below.
|
Job |
Normal duration (days) |
Minimum duration (days) |
Cost of crashing (INR per day) |
|
1-2 |
9 |
6 |
20 |
|
1-3 |
8 |
5 |
25 |
|
1-4 |
15 |
10 |
30 |
|
2-4 |
5 |
3 |
10 |
|
3-4 |
10 |
6 |
15 |
|
4-5 |
2 |
1 |
40 |
Consider the overhead total costs of INR. 60 per day
If the optimum length of schedule is 15 days, then the total cost of the project will be ________INR.
Enter numerical value using the virtual keypad. Round off where necessary.