In a wastewater treatment plant, primary sedimentation tank of dimension 25 × 5 m is designed at an overflow rate of 0.025 m3/s/m2. If the depth of liquid is 2.5 m and length of weir is 75 m. Calculate the weir loading rate (in m3/day/m) __________
Enter numerical value using the virtual keypad. Round off where necessary.