Consider the following activity for the total project:
|
Activity |
Immediate Predecessors |
Duration (Days |
|
A |
- |
10 |
|
B |
- |
9 |
|
C |
A |
9 |
|
D |
A |
8 |
|
E |
B |
7 |
|
F |
B |
11 |
|
G |
D, E |
5 |
1
25 days
2
23 days
3
21 days
4
19 days