Determine the probability (in percentage) of completing the project in 35 days for the following network given with the time estimates (in days) for each activity.

The probability (in percentage) corresponding to the different value of normal deviate are as follows:

Normal deviate

Probability

0.9

81.59

1.0

84.13

1.1

86.43

Enter numerical value using the virtual keypad. Round off where necessary.