A network is found by the following activities.The total float of the activity E and free float of activity D (in days) are respectively?

Activity

Activity Name

Activity Duration (days)

10-20

A

8

10-30

C

13

10-40

B

16

20-60

D

11

30-50

G

5

40-50

F

17

40-60

E

14

50-60

H

10

1
13 and 24 
2
24 and 13 
3
0 and 13
4
24 and 0 