engineering recuitment GATE CE 2023-24 Test Series Construction Materials and Management Project Planning PERT
A network is found by the following activities.The total float of the activity E and free float of activity D (in days) are respectively?
|
Activity |
Activity Name |
Activity Duration (days) |
|
10-20 |
A |
8 |
|
10-30 |
C |
13 |
|
10-40 |
B |
16 |
|
20-60 |
D |
11 |
|
30-50 |
G |
5 |
|
40-50 |
F |
17 |
|
40-60 |
E |
14 |
|
50-60 |
H |
10 |
1
13 and 24
2
24 and 13
3
0 and 13
4
24 and 0