A project consists of eight activities. The time required for each activity and its immediate predecessor(s) are given in the table below.
|
Activity |
Activity time (in days) |
Immediate predecessor(s) |
|
A |
2 |
- |
|
B |
3 |
- |
|
C |
2 |
A |
|
D |
4 |
A, B |
|
E |
4 |
C |
|
F |
3 |
C |
|
G |
X |
D, E |
|
H |
2 |
F, G |
If the project completion time using critical path method (CPM) is 15 days, then the value of X (in days) is ________. [in integer]