A small production unit now works 6 days per week with 3 ½ hours of first shift every one of the 6 days and 3 hours of second shift for each of the first 5 days. Wage negotiations led to an agreement to work on 5 days a week with both shifts together clocking 7 ½ hours per day with an 8% increase in weekly wages. How much change in the hourly production would mean parity in the agreement for both management and employees?
1
3.68%
2
2.15%
3
1.82%
4
1.33%