The time estimates in days are obtained from four contractors P, Q, R, S for executing a particular job are as under

Contractor

Optimistic time

(t0)

Most likely time

(tm)

Pessimistic time

(tP)

P

5

10

13

Q

6

9

12

R

5

10

14

S

4

10

13

1
Contractor Q is more certain about completing the project in time.
2
Contractor P is more certain about completing the project in time.
3
Expected Completion time by Contractor P is 9.67 days
4
Expected Completion time by Contractor Q is 9 days